Romania
2001 to 2003
New Container South Port Container Terminal in Constanza, Romania (EU)
Client: Compania Naționalǎ Administrația Porturilor Maritime Constanța
Company: Penta Ocean Construction Ltd
Position held: Construction Manager Electrical & MEP Works
Projects:
The Constanta Port, which faces the Black Sea, is Romania’s largest trade port. A terminal yard, crane foundations, and a construction control building were constructed to accommodate the sudden increase in container traffic. This project has received excellent reviews for total construction quality and design, and won the 2004 Award in Architectural Excellence from the Romanian Ministry of Transport, Constructions and Tourism. Construction Period: January, 2002 – June, 2003. New Container Terminal in Constanza consisting of Main gate, Container Freight Station, Administration building, Maintenance workshop, Grid/Substations 110/33/6,6kV and OHL 110kV & 33kV (110kV 15km and 33kV 40km).
Penta Ocean Construction Ltd Scope of work was as follows:
New Container Terminal in Constanza consisting of Main gate, Container Freight Station, Administration building, Maintenance workshop, Grid/Substations 110/33/6,6kV and OHL 110kV & 33kV (110kV 15km and 33kV 40km). Construction Period: January, 2002 – June, 2003.
Project was completed within time and budget